We have a requirement to upgrade our SAP HANA system system from SPS06 to SPS07, but I have below queries on the same:
1) Do we need to consider any Notes before applying the upgrade for pre and post steps (as per my knowledge we have to consider post upgrade note: 1962472, are there any other too?)
2) As per my knowledge, we just need to stop SAP app systems and then backup of HANA system
3) Also we have a distributed environment in our landscape (three multiple hosts), what could be the upgrade approach, is it same as like single host environment (as /hana/shared will be the common to all distributed hosts)
Could anyone clarify my questions please.
Also for your information we have BW systems on top of HANA DB
Thanks very much in advance !